Members of the workflow  
 information  
 before the start of the first part of the information -  
 1, bid notices and construction permits -  
 2, Construction Contract -  
 3, commissioned by the Commissioner of Works Supervision Contract -  
 4, examination and approval of construction plans and construction drawings of the book review -  
 5, the quality of supervision and registration form -  
 6, elements of quality supervision and quality monitoring tests, the program of work -  
 7, Geotechnical Engineering Investigation Report -  
 8, construction drawing Mixed Record -  
 9, by the Commissioner (or owners) to approve the construction design or construction programs -  
 10, begins the report -  
 11, Quality Management System Registration Form -  
 12, the construction site quality control inspection records -  
 13, technical tests, records -  
 14, measurement of positioning records -  
 -  
 -  
 -  
The second part of the data quality acceptance  
 -  
 1, the foundation trough records -  
 2, pile construction quality inspection reports -  
 3, ground handling project quality inspection reports -  
 4, foundation and basis for acceptance of quality of segment reporting -  
 5, main structure of the division of engineering quality inspection reports -  
 6, a special division engineering quality inspection reports -  
 7, line laying and inspection reports -  
 8, contained in the foundation and basic sub-division and division, breakdown of quality acceptance inspection lot records -  
 9, the main structure contains sub-divisions and divisions, sub, quality acceptance inspection lot records -  
 10, decoration segment and sub segment contained, breakdown of quality acceptance inspection lot records -  
 11, the roof segment and sub segment contained, breakdown of quality acceptance inspection lot records -  
 12, water supply, drainage and heating segments and contains sub-division breakdown of quality acceptance inspection lot records -  
 13, Electrical Division, and contained in the sub-division breakdown of quality acceptance inspection lot records -  
 14, Intelligence Division, and contains sub-division breakdown of quality acceptance inspection lot records -  
 15, Ventilation and Air Conditioning Division and contains sub-division breakdown of quality acceptance inspection lot records -  
 16, the elevator division, and contained sub-division breakdown of quality acceptance inspection lot records -  
 17, sub-units contained unit project and final acceptance of project quality records -  
 18, outside the project segments (sub-segment), sub-items, quality acceptance inspection lot records -  
 -  
 third part of the test data -  
 1, cement physical performance test report -  
 2, sand, stone and inspection reports -  
 3, the strength grade of concrete mix test report -  
 4, strength of concrete sample tables, evaluation forms and test report -  
 5, the strength grade of mortar mix test reports -  
 6, mortar specimens and test report strength tables -  
 7, brick, stone, block strength test report -  
 8, steel, mechanical and bending properties of steel welded joint inspection report and the tensile, bending test report or reinforced mechanical connectors Inspection Report -  
 9, tendons, steel, mechanical properties of strand approach reinspection report -  
 10, Pile Foundation Engineering Test Report -  
 11, steel structure engineering test report -  
 12, curtain wall engineering test report -  
 13, water-proof material test report -  
 14, the outer metal and plastic doors, windows test report (including material and three of) -  
 15, exterior wall tile drawing strength test report -  
 16, construction (structures) lightning protection device acceptance test report -  
 17, there are special requirements or design requirements of backfill compaction test report -  
 18, quality acceptance of the other test report -  
 19, basement waterproofing effect inspection records -  
 20, a water test records required by the ground water -  
 21, roof water spray test records -  
 22, pumping (wind) Road inspection records -  
 23, energy saving, insulation test records -  
 24, piping, equipment strength and leak test records -  
 25, system cleaning, irrigation, water, pass the ball test records -  
 26, lighting the whole load test records -  
 27, large light fastness test records -  
 28, electrical equipment debug logging -  
 29, Electrical Engineering, grounding, insulation resistance test records -  
 30, refrigeration, air conditioning, plumbing strength and leak test records -  
 31, refrigeration equipment test run debug logging -  
 32, ventilation and air conditioning system test run debug logging -  
 33, air flow, temperature test records -  
 34, elevator equipment, package inspection records -  
 35, the elevator load testing, safety devices, inspection records -  
 36, lift ground, insulation resistance testing records -  
 37, the elevator test run debug logging -  
 38, intelligent building system commissioning records -  
 39, intelligent building systems and equipment commissioning function test records -  
 40, units (sub-unit) project safety and function test all required measuring, testing, testing, inspection, testing, commissioning, trial run record -  
 Part IV materials, products, components, fittings and other certification information -  
 1, the cement factory certification (including the reinforcement of the report 28 days) -  
 2, brick, block factory certification -  
 3, reinforced, prestressed, steel wire, steel cable, the sleeve factory certification -  
 4, steel piles, precast concrete piles, prestressed concrete pipe factory certification -  
 5, steel engineering components and accessories, materials, factory certification -  
 6, curtain wall parts, materials, factory certification -  
 7, waterproofing material factory certification -  
 8, metal and plastic doors and windows of the factory certification -  
 9, electrode and flux factory certification -  
 10, precast, ready-mixed concrete certificate -  
 11, drainage and heating engineering materials to the factory certification -  
 12, building electrical engineering materials, equipment, factory certification -  
 13, ventilation and air conditioning engineering materials, equipment, factory certification -  
 14, elevator engineering equipment factory certification -  
 15, intelligent building construction materials, equipment, factory certification -  
 16, construction requirements and other certification -  
 -  
 -  
Part V of the construction process  
 information -  
 1, design changes, negotiation records -  
 2, engineering survey, put the line records -  
 3, pre-screening, self-inspection, mutual inspection, the transfer of inspection records -  
 4, construction (structures) settlement observation survey record -  
 5, new materials, new technologies, new processes construction records -  
 6, concealed work records -  
 7, construction of the log -  
 8, concrete opening report -  
 9, concrete construction records -  
 10, measured at random mix concrete records -  
 11, project quality accident report sheet -  
 12, project quality accident and the cause of the accident investigation, treatment records -  
 13, project quality rectification notice -  
 14, partial suspension of the construction project notice -  
 15, project quality applications for rectification of the report and return to work -  
 16, works resumed Notice -  
 -  
 -  
Part VI  
 necessary, additional information -  
 1, survey, design, supervision and construction (including sub-) proof of qualification units -  
 2, construction, survey, design, supervision and construction (including separation) units of change and reasons for change -  
 3, survey, design, supervision units practice practitioners Certification -  
 4, the construction (including subcontractors) units on-site management and the types of skilled workers, salespersons posts prove that -  
 5, by the construction unit (owner) agreed to recognize the planning or supervision of the Commissioner of the Regulations -  
 6, witnessed the construction of units stationed in the power of attorney or power of attorney on behalf of site design -  
 7, construction and design units stationed in the power of attorney or power of attorney on behalf of site design -  
 8, Other -  
 -  
 -  
 -  
 -  
 -  
 Part VII of the completion data -  
 1, the construction unit project completion report -  
 2, completion of the project quality supervision unit evaluation report -  
 3, documents and investigation units in the implementation of survey inspection report -  
 4, the design and implementation of design documents, unit inspection report -  
 5, final acceptance of construction quality submissions or units (sub-unit) project completion and acceptance of quality records -  
 6, completion and acceptance of problem rectification notice -  
 7, completion and acceptance of problem rectification acceptance submissions -  
 8, project completion and acceptance of conditions with the notice and notice of final acceptance of the reorganization -  
 9, units (sub-unit) project quality control data verification record (quality assurance data review of records) -  
 10, units (sub-unit) project safety and function test data and the main function of random inspection records -  
 11, units (sub-unit) Appearance quality inspection records (perception of the quality assessment form) -  
 12, direct marketing residential real estate financing of users or employees to sign Feedback -  
 13, project quality warranty contracts (Book) -  
 14, construction project completion acceptance report (completed by the construction unit) -  
 15, built drawings (including Intelligent Building Division) -  
 -  
 construction quality supervision and archiving data -  
 1, Construction Project Quality Supervision Registration Form -  
 2, examination and approval of construction drawings and construction drawings review -  
 3, unit project quality supervision program -  
 4, construction engineering quality supervision and tests, tests, notice of the meeting points -  
 5, construction engineering quality supervision records -  
 6, Construction Quality Management System Registration Form -  
 7, the construction site quality control inspection records -  
 8, foundation, pile construction quality supervision and inspection inspection notice -  
 9, the foundation pile trough project quality records and inspection reports -  
 10, foundation, pile construction quality inspection records -  
 11, the design of units issued (or recognition) of the foundation and foundation treatment works treatment measures the quality of inspection reports -  
 12, foundation and foundation division notice of project quality supervision and inspection and acceptance of inspection reports -  
 13, groundwork and foundation engineering quality check division records -  
 14, the main structure of division notice of project quality supervision and inspection and acceptance of inspection reports -  
 15, project quality verification of the main structure of division records -  
 16, a special part of the notice of project quality supervision and inspection and acceptance inspection report -  
 17, line laying project quality supervision and inspection and acceptance report of inspection notice -  
 18, steel, mechanical and bending properties of steel welded joint inspection report and the tensile and bending test report -  
 19, prestressed, steel, mechanical properties of strand approach reinspection report -  
 20, cement physical performance test report -  
 21, strength of concrete sample tables, rating scale test report -  
 22, assembly or inspection certificate prefabricated structural performance and construction joints, patchwork full of concrete under construction, all fully loaded strength test specimen reported -  
 23, waterproof concrete, sprayed concrete compressive strength, impermeability test reports and test reports force bolt anti-aside -  
 24, Foundation Treatment Foundation, and various types of composite foundation after construction of the foundation strength (capacity) test results -  
 25, Pile Foundation Pile Test Report -  
 26, mortar strength and the specimen test report tables -  
 27, brick, stone, brick intensity Inspection Report -  
 28, construction materials and indoor environment, hazardous materials testing report -  
 29, waterproof materials (including water stop and joint sealing material article), thermal insulation and sealing materials reinspection report -  
 30, metal and plastic exterior doors, windows re-inspection report (including material, wind resistance, air permeability, water permeability) -  
 31, exterior wall tile drawing strength test report -  
 32, various types of elevators, escalators, automatic installation of the machine to install sidewalk inspection reports -  
 33, various types of covert acceptance of equipment installation, system linkage, system debugging and system installation inspection records -  
 34, the thickness of concrete floor panels random drilling records -  
 35, project quality accident report sheet -  
 36, project quality and project a rectification notice to suspend the construction of local notices -  
 37, project quality and project quality submissions resumed resumed Notice -  
 38, units (sub-unit) project quality control data verification record (quality assurance data review of records) -  
 39, units (sub-unit) project safety and function test data and the main function of random inspection records -  
 40, units (sub-unit) Appearance quality inspection records (perception of the quality assessment form) -  
 41, the construction unit project completion report -  
 42, completion of the project quality supervision unit evaluation report -  
 43, survey documents and investigation units in the implementation of the inspection report -  
 44, the design and implementation of design documents, unit inspection report -  
 45, construction project completion acceptance report -  
 46, works supervision and inspection of final acceptance notice -  
 47, quality assurance data verification records -  
 48, units (sub-unit) project completion and acceptance of quality records (quality of the project completion and acceptance of submissions) -  
 49, re-organize the final acceptance notice -  
 50, retest completion of the project submissions -  
 51, notice of completion and acceptance of problems and problem rectification rectification acceptance of submissions -  
 52, project quality warranty contract -  
 53, units (sub-unit) engineering quality monitoring report -  
 Note: curtain wall, steel structure and set of data storage grid quality supervision station -  
 -  
 -  
 -  
 -  
 - 
		
	
		
		
		
		
		
	
	 |